It appears to be just an outline, this outline will need to be completed and filled out by next week,
as a full draft.
Remember There is Only 2 Weeks till the deadline for this report!
admin wrote:I hope that you have all received a email from bai li, it would appear that we need to make some modifications to the report before we submit a final copy of the report.
These are the suggestions from bai li.
1. introduction
(normally chapter 2 is for literature reviews)
2. system design and implementation
2.1 requirements (including all sorts of requirements, functional and architectural etc)
2.2 program design
2.3 system implementation
3. user interface design and implementation
3.1 requirements
3.3 system structure
3.3 user scenarios
4. applications (this is missing in the interim report)
5. conclusions
Additionally we received a score or 73% on the interim report, Congratulations everyone, thats a 1st!